The excavation phase of the North Berm repair was completed Friday morning, May 8, at approximately 8:30 am. Beginning Monday, May 11, field work on the North Berm will include final preparation of the slope for installation of longer term cover and stormwater controls.
Mobilization for the North Berm repair work began April 13, with excavation starting on April 21. The final treatment on the North Berm slope and the demobilization phase of this work is expected to take at least one week.