Field work at the Ascon Landfill Site during the week of August 26 is planned to include:
- Removal of existing chain link fence and use of temporary fence in preparation for installation of 16-foot barrier fence along residential-facing public streets Hamilton Avenue and Magnolia Street; there is additional onsite security during this work
- Tree removal in the southeastern zone to prepare for installation of 16-foot barrier fence along Magnolia Street; this work will involve the use of wood chippers as trees are removed which will produce noise within City permit limits during work hours
- Dust and odor mitigation measures continue to be implemented
- Air quality monitoring continues
- Weed abatement and removal as necessary
- 24-hour onsite security continues
- No work will be conducted at Ascon on the Labor Day holiday, September 2