Field work at the Ascon Landfill Site during the week of August 26 is planned to include:
- Removal of existing chain link fence and use of temporary fence in preparation for installation of 16-foot barrier fence along residential-facing public streets Hamilton Avenue and Magnolia Street; there is additional onsite security during this work
- Tree removal in the southeastern zone to prepare for installation of 16-foot barrier fence along Magnolia Street; this work will involve the use of wood chippers as trees are removed which will produce noise within City permit limits during work hours
- Dust and odor mitigation measures continue to be implemented
- Air quality monitoring continues
- Weed abatement and removal as necessary
- 24-hour onsite security continues
- No work will be conducted at Ascon on the Labor Day holiday, September 2
Have a Question or Concern?
Please contact the Ascon community information line at 714-388-1825 or email [email protected]. If there is a potential emergency, please call 911. Sign up for AsconAlert, an opt-in community alert system for the Ascon project here.
Stay Informed
Please subscribe for email updates.
Information provided through this website may be shared with the Ascon team, Ascon consultants, Ascon responsible parties and government agencies. Read our Privacy Policy.