Field work at the Ascon Landfill Site during the week of July 1st is planned to include:

  • Weed abatement and brush removal beginning July 1 to July 3
  • Preparation for future cleanup work in the Pit F enclosure
  • Preparation for installation of taller barrier fence along Hamilton Avenue and Magnolia Street, subject to City of Huntington Beach permit approval; this activity will include some grading and tree or brush removal prior to barrier installation
  • Dust and odor mitigation measures will continue to be implemented, including the use of Posi-Shell® (see June 19 post)
  • Active measures will continue to be taken to monitor air quality
  • 24-hour onsite security continues

Recent Posts

SEE ALL UPDATES