Field work at the Ascon Landfill Site during the week of July 1st is planned to include:
- Weed abatement and brush removal beginning July 1 to July 3
- Preparation for future cleanup work in the Pit F enclosure
- Preparation for installation of taller barrier fence along Hamilton Avenue and Magnolia Street, subject to City of Huntington Beach permit approval; this activity will include some grading and tree or brush removal prior to barrier installation
- Dust and odor mitigation measures will continue to be implemented, including the use of Posi-Shell® (see June 19 post)
- Active measures will continue to be taken to monitor air quality
- 24-hour onsite security continues
Have a Question or Concern?
Please contact the Ascon community information line at 714-388-1825 or email info@asconhb.com. If there is a potential emergency, please call 911. Sign up for AsconAlert, an opt-in community alert system for the Ascon project here.
Stay Informed
Please subscribe for email updates.
Information provided through this website may be shared with the Ascon team, Ascon consultants, Ascon responsible parties and government agencies. Read our Privacy Policy.