Field work at the Ascon Landfill Site during the week of May 20th is planned to include:

  • Material will be graded in the Northwest corner;
  • The areas along Hamilton Ave. and Magnolia St. will be further excavated and graded;
  • Onsite concrete will be broken for reuse, this material is watered for dust mitigation prior to and during this action;
  • The construction of the Pit F Enclosure near Magnolia Street is expected to be completed;
  • Active measures will be taken to monitor air quality and mitigate odor and dust, in work zones and throughout the Site.