Field work at the Ascon Landfill Site during the week of November 18th is planned to include:

Beginning Monday, November 18, field activities will include:

  • “Winterizing” field activity to prepare the Site for the winter rainy season by implementing best management practices for stormwater management, in compliance with the Santa Ana Regional Water Quality Control Board permit (For more information, please see the October 8 post on Project Updates)
  • A long-term soil cover slurry, Posi-Shell®, will be applied in excavated areas as part of winterizing activities relating
  • Delivery of supplies for winterizing field activities
  • Dust and odor mitigation measures continue to be implemented
  • Air quality monitoring continues
  • Weed abatement and removal as necessary
  • 24-hour onsite security continues