DID YOU KNOW?

Clean soil will be brought onsite for future use starting the week of July 28, 2025. This clean soil import work includes transporting a total of approximately 40,000 cubic yards of clean soil onsite through an approved truck route (pictured below) with dust, dirt and traffic mitigations in place to minimize inconvenience to the community. By importing clean soil sooner than originally planned we hope to potentially shorten the overall project schedule.

Approved project haul route

Approved project haul route.

For more details on the upcoming clean soil import work, please reference the “Field Work” section below. The Ascon team will keep the community updated on this work through the project’s Weekly Site Updates sent Monday mornings. If you have any questions, please contact the Ascon community information line at 714-388-1825 or email the project team at info@asconhb.com with any questions.

SITEWIDE ACTIVITIES

  • FIELD WORK: Excavation work will continue in the northern and eastern areas of Ascon this week, depending on weather and Site conditions.

    Here is what you can expect to see during clean fill soil import work:

    • As many as 100 trucks will arrive onsite per day. Work is planned for Monday through Friday, between 7 a.m. and 6 p.m. for four to eight weeks. Work may occur on Saturdays, if needed.
    • Trucks will enter from Hamilton Ave. (green arrow on map) and exit on Magnolia St. (orange arrow on map). Trucks will avoid the major intersection of Hamilton and Magnolia per the project’s approved haul route plan.
    • The Ascon team will monitor soil import trucks to ensure drivers follow the approved route, and we will address any variance from the approved route. Dust mitigation and traffic control measures will be in place during this clean soil import, including continued onsite dust mitigation measures. We will also conduct additional street cleaning outside project site entrance and exit areas.

    The Ascon information table will be set up in Edison Park across from the Site on days that northern excavation and initial clean soil import work is occurring. Offsite odor monitoring technicians, in Ascon-labeled orange safety vests, will be monitoring outside the Site.

    During this phase of work, personnel may be onsite on Saturdays to conduct Site and equipment maintenance, from 7 a.m. – 5 p.m. No excavation work is planned to occur during this Saturday maintenance work.

  • INSPECTIONS:

    • DTSC is the lead regulatory agency for the Ascon project and conducts inspections at Ascon. Their inspection reports can be found on the online DTSC database, Envirostor.
    • The City of Huntington Beach continues its regular stormwater inspections of Ascon. Ascon remains in compliance with stormwater pollution prevention requirements.
    • Regular inspections are conducted by Orange County Mosquito and Vector Control District of areas of the Ascon Site where water may be detained. Active mitigation measures are implemented by Vector Control to protect the community, as well as onsite workers, from mosquitoes.
  • SECURITY: 24-hour, 7 days per week, onsite security continues during construction activities. Security is not always visible at the entrance gates. Unannounced visitors without official business or agency oversight of Ascon are not permitted to enter the Site. Trespassers will be reported to the Huntington Beach Police Department and DTSC.

    You may see: You may see flashlights or headlights from vehicles after dark concluding daily activities and providing security at the 38-acre Site.

    In an emergency: If you see or hear something that appears urgent, please call the Huntington Beach Police Department at 911 first, then the Ascon community information line, 714-388-1825. Calls to the Ascon information line are automatically logged and relayed by text and email to the Ascon team.

AIR MONITORING

Dust and total VOC monitoring is conducted 24/7 at upwind and downwind stations on the Ascon Site documenting effective dust control measures. This is in addition to 24/7 air monitoring at the neighborhood stations.

Where to find air monitoring data and live stream weather: Sitewide and live streaming weather conditions from the Ascon site are found on the Actively Monitoring Air Quality page on asconhb.com. To view archived air monitoring results posted by DTSC on Envirostor — including weekly field inspections by DTSC that include air monitoring observations — click on “Community Involvement Documents” and scroll to “Updates and Information.”

SAFETY MESSAGE

SEE SOMETHING? HAVE A QUESTION? Call our information line: 714-388-1825 or email us at info@asconhb.com

DRONES: Drone flights over Ascon can create worker and Site safety issues. Please don’t fly drones over sensitive onsite equipment and the power lines along the perimeter of Ascon. We appreciate the community’s assistance.

ENTRANCE AND EXIT GATES: Entering the Ascon site is prohibited to those who are not authorized. The community is asked to keep a safe distance from both entrance and exit gates at Ascon, and refrain from parking, walking, or standing in these areas. The gates on Magnolia Street and Hamilton Avenue may open unexpectedly for workers and site inspections, as well as supply delivery and removal.

PEDESTRIANS: Your safety is important! Pedestrians have been observed walking next to Ascon along Magnolia and Hamilton streets (adjacent to the concrete fence base where there currently is no sidewalk). We encourage pedestrians to observe public pathway signage and use the sidewalks on the east side of Magnolia and the north side of Hamilton.

Recent Posts