Cleanup Activities
As we engage with our neighbors to complete the remediation work, the health and safety of the Huntington Beach community remains our highest priority.
What’s Been Done
Over the past 20 years, the Ascon team has made significant progress on cleanup efforts. Multiple cleanup actions were completed at the Ascon Landfill Site from 2005 to 2023. Together, the following actions included the removal of approximately 128,000 cubic yards of waste materials.
2005 – 2006
Emergency work was conducted to remove materials that were pressing against a decades-old earthen berm, the area was reinforced and extensive stormwater management actions were conducted after a 200-year rain event.
2007 – 2017
Extensive field investigations and analysis led to the development of various environmental documents that will determine the cleanup path moving forward. These received significant public review and input, including through community meetings.
2017 – 2019
Fieldwork was conducted to solidify much of the Lagoon 5 area, enabling closure of long-inactive, buried oil wells dating from the 1920s, as preparation for the final cleanup.
2019 – 2022
The final cleanup field work was initiated, but work was paused in June 2019 at DTSC’s direction to address community concerns. In 2020, an emergency repair of the northwest berm occurred, and borings and sampling for a technical sitewide odor analysis were taken. Pit F material was excavated and the tent was removed.
2023 – 2024
In coordination with DTSC, Ascon developed a pilot testing workplan to test Engineered Misting Containment (EMC) and Soil Vapor Extraction (SVE) pre-treatment onsite. Pilot work began in June 2023 and was completed in October 2023. Ascon will submit pilot test findings to DTSC and work to develop a restart plan and schedule. A public meeting will be held in advance of restart. Learn more about completed pilot work here.
Current Cleanup Plan
In 2015, the California Department of Toxic Substances Control (DTSC) approved a Final Remedial Action Plan (RAP) outlining cleanup activities for the Ascon Site. The cleanup plan was approved following a rigorous, multi-year public review and a formal Environmental Impact Report (EIR) process per the California Environmental Quality Act (CEQA).
Since work began in January 2019 on the activities outlined in the RAP, approximately a third of the excavation work has been completed.
The cleanup plan includes the removal and offsite disposal of impacted soils from the former Pit F, which was completed in 2021. Learn more about the Pit F work and telemetry air monitoring here. The remaining waste and soils will be excavated, graded, and covered in an engineered containment area that will be underneath a multi-layered environmental cap. After the final excavation and grading is complete, the environmental cap is constructed with geomembrane barriers, clean soils, and planted with native, drought-tolerant plants. The property will continue to be inspected and maintained long-term as secured open space with residential-style perimeter fencing. See what Ascon will look like at Future of the Site.
Current Cleanup Status
Since work was paused in June 2019 at DTSC’s direction to address community concerns about dust and odor, the Ascon team has introduced additional health and safety enhancements to protect the community. Under direction and oversight from DTSC, Ascon conducted emergency northern berm repair work in 2020, Pit F excavation and tent removal in 2021 and pilot work onsite testing in 2023. Ascon is currently working with DTSC to develop a restart plan based on pilot test findings.
Learn more about Engineered Misting Containment and Soil Vapor Extraction pre-treatment pilot work. Learn more about the Pit F excavation work here.
Check out Site Updates to find out what our team is doing this week on Site and in the community.
Investigations Guide Cleanup Actions
Numerous Site investigations have taken place over more than 30 years, including soil sampling, groundwater monitoring and air monitoring. We are using what we learned from the 2023 pilot work and the following investigations to guide our cleanup approach:
View the Revised Feasibility Study approved by DTSC in September 2007 to learn more.
Sampling and investigations conducted since 2002 found the impacts to shallow groundwater are contained within the Site boundaries.
Air monitoring is used to ensure air quality meets health-protective screening levels. Click here to learn more about air monitoring at the Site.
Frequently Asked Question
Our team is maintaining the Site, conducting air and groundwater monitoring, performing health and safety enhancements to control dust and odors, and providing Site security. These actions do not involve any remediation work.
Site Documents
- Final Remedy SWPPP
- Ascon Public Participation Plan
- Safety Data Sheets (SDS) for Weed Abatement
- Safety Data Sheets (SDS) for Odor Suppressants
- Safety Data Sheets (SDS) for Soil Stabilizer
- DTSC Initial Study - RAP for Ascon Landfill Site Draft EIR
- Appendix A - NOP Initial Study
- Appendix B - Air Quality
- Appendix C - Biological Resources Data
- Appendix D - Greenhouse Gas Assessment Files
- Appendix E - Health Risk Assessment
- Appendix F - Noise Worksheets
- Appendix G - Traffic Study
- Appendix H - Alternatives Analysis Worksheets
- Appendix I - Cultural Resources Data
- Recirculated Draft EIR
- Final Environmental Impact Report (EIR)
- RAP CEQA Findings and Statement of Overriding Considerations
- RAP Notice of Determination (NOD)
-
Appendices
- Ascon IRM Approval IRM Completion Report
- App-A-1 Ascon IRM Approval Letter 05-10-10
- App-A-2 Ascon IRM MND 05-10-10
- App-A-3 Ascon IRM Approval Letter 05-12-10
- App-A-4 Ascon IRM MMRP 05-10-10
- App-A-5 Ascon IRM MND Addendum 7-15-10
- App-A-6 Ascon IRM Addendum NOD 7-16-10
- App-A-7 Ascon IRM Lagoon 3 NOE 11-23-10
- App-A-8 Ascon IRM MND Addendum 2 12-7-10
- App-A-9 Ascon IRM Amend 2 NOD 12-7-10
- App-B-1 Well Destruction Permit
- App-B-2 Ascon IRM SCAQMD 1150-1166 permit
- App-B-3 AQMD Notification Form Mailed 07-23-2010
- App-B-4 AQMD Notification Mailed 08-06-2010
- App-B-5 Ascon IRM Haul Permit 06-22-10
- App-B-6 CDP Notice of Action 3-4-10
- App-B-7 CDP Notice of Final Action 3-18-10
- App-B-8 Ascon CDP 2009-007 RTC 06-22-10
- App-B-9 Ascon IRM Grading Permit
- APPENDIX K - Weekly Perimeter Air Monitoring Data Summaries
- APPENDIX L - Air Monitoring Laboratory Analytical Reports
- APPENDIX M - QC Checklist Sheets for Laboratory Reports
- App-O-1 Ascon IRM AQ-1(onsite)-rev
- App-O-2 Ascon IRM AQ-2(haulers)
- App-O-3 Ascon Mitigation Agreement (07-09-10)
- App-O-4 RTC transfer confirmations
- App-O-5 Ascon IRM weekly eq hours
- App-O-6 fleet change analysis (10-8-10)
- App-O-7 Ascon IRM URBEMIS files rev
- App-O-8 Ascon IRM Daily NOx Emissions Summary rev
- App-P-1 Sensitive Biological Resources Training Presentation
- App-P-2 Sensitive Biological Resources Training Memorandum
- ASCON Fence Monitoring Memo 2010-08-03
- ASCON Fence Monitoring Memo 2010-08-10
- ASCON Fence Monitoring Memo 2010-08-17
- ASCON Fence Monitoring Memo 2010-08-24
- ASCON Fence Monitoring Memo 2010-08-31
- ASCON Fence Monitoring Memo 2010-09-07
- ASCON Fence Monitoring Memo 2010-09-14
- ASCON Fence Monitoring Memo 2010-09-21
- ASCON Fence Monitoring Memo 2010-09-28
- ASCON Fence Monitoring Memo 2010-10-05
- ASCON Fence Monitoring Memo 2010-10-12
- ASCON Fence Monitoring Memo 2010-10-20
- ASCON Fence Monitoring Memo 2010-10-26
- ASCON Fence Monitoring Memo 2010-11-02
- ASCON Fence Monitoring Memo 2010-11-09
- ASCON Fence Monitoring Memo 2010-11-16
- ASCON Fence Monitoring Memo 2010-11-23
- ASCON Fence Monitoring Memo 2010-11-30
- ASCON Fence Monitoring Memo 2010-12-07
- ASCON Fence Monitoring Memo 2010-12-14
- ASCON Fence Monitoring Memo 2010-12-21
- ASCON Fence Monitoring Memo 2010-12-28
- ASCON Fence Monitoring Memo 2011-01-04
- ASCON Fence Monitoring Memo 2011-01-11
- ASCON Fence Monitoring Memo 2011-02-08
- ASCON Fence Monitoring Memo 2011-02-15
- ASCON Fence Monitoring Memo 2011-02-22
- ASCON Fence Monitoring Memo 2011-03-01
- ASCON Fence Monitoring Memo 2011-03-08
- ASCON Fence Monitoring Memo 2011-03-15
- App-P-4 Ascon MMRP - IRM MND - Monitoring Results June 2011 COMPLETE
- Addendum to Ascon IRM MND
- NOD - Ascon IRM
- Ascon Landfill IRM Public Notice
- NOE - Ascon IRM
- NOD - Ascon IRM MND Addendum
- Addendum to Ascon IRM MND
- Work Notice Interim Removal Measure (IRM) Workplan
- DTSC Response to Public Comments on the Interim Removal Measure
- Interim Removal Measure Workplan Approval - MND - MMRP
- Interim Removal Measure Technical Memorandum
- City of Huntington Beach Coastal Development Permit Conditional Approval Letter
-
APPENDIX A - CEQA Documents
- APPENDIX B - Permits
-
APPENDIX E - Hamilton survey
-
APPENDIX J - Wind Rose Diagrams
-
APPENDIX N - Level IV Data Validation Reports
-
APPENDIX O - MMRP Air Quality Measures
-
APPENDIX P - MMRP Biological Measures
-
App-P-3_Biologist's Weekly Compliance Reports
-
APPENDIX Q - Public Participation
-
Figures
-
Appendices
- Appendix B (Biological Conditions 2004)
- Appendix C (OCWD 2004 well survey rpt)
- Appendix D (PS3 field activities)
- Appendix E (Data Tables)
- Appendix F (Emissions - flux)
- App F Att F1 (Flux Tech Memo)
- App F Att F1 Attachment A (Data Sheets) (1 of 2)
- App F Att F1 Attachment A (Data Sheets) (2 of 2)
- App F Att F1 Attachment B (COCs)
- App F Att F1 Attachment C (Data Rpts) (1 of 5)
- App F Att F1 Attachment C (Data Rpts) (2 of 5)
- App F Att F1 Attachment C (Data Rpts) (3 of 5)
- App F Att F1 Attachment C (Data Rpts) (4 of 5)
- App F Att F1 Attachment C (Data Rpts) (5 of 5)
- App F Att F1 Attachment D (DHF Graphs)
- App F Att F2 (Emission potential)
- App F Att F3 (Index-Soil and Flux Rpts)
- Appendix G (Perimeter air data tables)
- Appendix H (NORM_calibration_log)
- Appendix I (Geotech)
- Appendix J (PTS Geotechnical Rpt)
- Appendix K (Stability)
- Appendix L (historic GW detections)
- Appendix M (Perimeter Air ROF)
- Appendix N (PS3 perim air tables-roses)
- Appendix O (Reevaluation o f Air Pathway Analysis)
- Appendix P (risk_RBC_calcs)
- Appendix Q (Remedy Volumes)
- Appendix R (Remedy Cost)
- Appendix S (O&M Cost)
- Appendix T (Post-Remedy Groundwater)
- Appendix U (index-soil rpts)
- INC0993
- INC1049
- INE0031
- INE0119
- INE0228
- INE0764
- INE0764-full
- INE0764_REVISION
- INE0765_REVISION
- INE0765-full
- INE0892-full
- INE0965-full
- INE1120-full
- INE1148-full
- INE1250-full
- INE1447
- INE1513
- INE1627_REVISION
- INF0242
- INF0549
- INF0844_REVISION
- INF0940_REVISION
- INF1488
- INF1737
- INF1826
- INF1828
- ING0001_REVISION
- ING0094
- ING0239
- ING1250
- Appendix V (index-fuel rpts)
- Appendix X (Old Treat and Pilot Studies)
- Appendix Y (Phase IX Treatability Studies)
-
Appendix A
-
Appendix F Attachments
-
Appendix F Att F1 Attachments
-
Appendix U
-
App U Lab Report-soil
-
Appendix V
-
App V Lab Reports-fuel
-
Appendix W
-
Appendix Y
-
Appendix Y Attachment Y1 (Workplan Addendum)
-
Appendix Y Attachment Y2 (Prima Rpt)
-
Appendix Y Attachment Y3 (lab rpts)
-
Figures
-
Appendices
- Appendix A
- Appendix B
- Appendix C Part 1
- Appendix C Part 2
- Appendix E Tidal Study Data
- Appendix E Final Tidal Study
- Appendix F
- Appendix G
- Appendix H
- Appendix I NAPL-PTS Report
- Appendix I NAPL - Zymax Report
-
Appendix D
-
Data Validation Reports
-
Appendix K
Have a Question or Concern?
Please contact the Ascon community information line at 714-388-1825 or email [email protected]. If there is a potential emergency, please call 911. Sign up for AsconAlert, an opt-in community alert system for the Ascon project here.
Stay Informed
Please subscribe for email updates.
Information provided through this website may be shared with the Ascon team, Ascon consultants, Ascon responsible parties and government agencies. Read our Privacy Policy.